MANILA, November 8, 2017 — Department of Transportation (DOTr) Secretary Arthur Tugade, National Economic Development Authority (NEDA) Secretary Ernesto Pernia, and Cabinet Secretary Jun Evasco successfully conducted the first test flight in the fully-paved runway of the New Bohol Airport in Panglao last November 6.

Currently, 1,800 meters out of the total 2,500 meters of the runway has already been fully-paved. An additional 300 meters will be added to extend the runway to 2,800 meters after the operationalization of the airport. The runway was engineered to accommodate seven aircraft at one time, including large aircraft for international flights.

Fast-tracking construction
Construction for the airport followed a 24/7 schedule upon the directive of Tugade. From the time the Duterte administration took over in July 2016, completion of the airport is now at 53.38%, a huge jump from the 6.48% completion recorded from June 22, 2015 to June 30, 2016.

The New Bohol (Panglao) airport is on track for completion by June 2018, and will start commercial operations by August.

The project was first undertaken by the Provincial Government of Bohol in 1996. The feasibility study, land acquisition activities, and detailed engineering design were completed by 2007.

However, the bidding failed in 2010 due to lack of funding. It was only then that the national government decided to implement the project under Public Private Partnership (PPP). It began construction in 2015 under the Japanese Airport Consultants (JAC) and Chiyoda-Mitsubishi Joint Venture (CMJV).

First eco-airport
The P7.8-billion project, with a terminal spanning 13,337 square meters, will serve as the premiere gateway to the province and the island paradise of Panglao, a thriving tourist destination. It was designed to be the country’s first eco-airport and “Green Gateway to the World,” which will be held to the highest standards of green and sustainable structures.

The airport will primarily use natural sunlight and air. However, areas where people stay for a longer period of time such as pre-departure sections, control rooms, and offices will be air-conditioned.

Solar panels will also be installed on the Passenger Terminal Building roof, which can cover around one-third of the airport’s energy requirement.

For additional energy efficiency, all internal lighting fixtures will use LEDs and most lighting switches will be equipped with motion detector control.

The New Bohol (Panglao) Airport is expected to accommodate 2 million passengers in its opening year alone, a huge jump from the 800,000 passengers currently being accommodated by the Tagbilaran airport.

The project is financed via Official Development Assistance by the Japan International Cooperation Agency (JICA).




If you enjoy reading our stories,
please help keep Mindanation up and running by donating any amount.
Your support will go a long way in keeping us going.

Facebook Comments

You may also like

US scientists predict more big earthquakes in 2018

WASHINGTON — If a prediction by two US